TRANSCO(2011) Contract No. N-11777(COMPLETED)
October 3, 2020
Shifting of 140MVA Power Transformer from Ghantoot to Al Wathba 220-33kV Substation
Project Manager – Engr. Jun Cris Lubang Civil Engineer – Yasser Semary Civil Engineer – Peter Andrews
Site Updates
April 01, 2012
May 1-6, 2012 - Protection Works / 140MVA Transformer Marshalling Kiosk / SF6 Filling for 220kV Bus duct
September 20, 2012 - 132kV GIS Circuit Breaker time-in test
Fixing of 11kV Cable from Transformer A to 11kV SwitchgearOTI & WTI Calibration for Transformer A & BCompleation of Fencing Works
September 11, 2012 - Earthing Works / Excavation Backfiling
Cable Tray Works / Installation of Gantry SupportInstallation of Lighting Pole / Installation of Fencing Gate
September 02, 2012 - Transformer A Test Preparation / Installation of Sunshields for GIS / Earthing Lightning Works -Container B
Backfilling for Earthing_GIS_NE area