CONTRACT NO. N-6878 (COMPLETED)
October 10, 2020
Supply and Installation of new 220/33 kV Mobile at Shamkha Area and Replacement of old Battery & Battery Chargers in Substations 220kV UAN
Project Manager : Mr. Anil Tandon
Site Updates
February 11, 2010 -
Group photos of Shamka Team headed by Project Manager Anil Kumar Tandon with Mr. Gerhard Siegel (Remcon Managing Partner). Mr. Sayed Imtiaz Ahmed & Mohd. Ali Zakaria Khan of Transco witnessed the testing activities. HIGH VOLTAGE TEST FOR 220kV CABLES together with 220kV GIS SWITCHGEAR at SHAMKHA Substation