TRANSCO Contract No. N- 11022
October 1, 2020
TRANSCO Contract No. N- 11022 TRANSCO N/A UAE Transferring and Installation of 132/11kV Mobile Station from YAS Island to Mussafah Area (M12) and associated works
Site Updates
December 17, 2012 - CT ratio & Polarity check
Installation of new Protection Panel
November 29, 2012 - HV test at Container 'A' & 'B'
Plugging termination of 11kV cable at Container 'A' & 'B'
November 10, 2012 - 132kV Cable Termination at Transformer No. 2.
132kV Ring CT testing at Bay E01 & E02 (witnessed by Transco)Auxilliary Transformer No. 1 Testing (Witnessed by ADDC)CT installation
September 20, 2012 - 132kV GIS Circuit Breaker time-in test
Fixing of 11kV Cable from Transformer A to 11kV SwitchgearOTI & WTI Calibration for Transformer A & BCompleation of Fencing Works
September 11, 2012 - Earthing Works / Excavation Backfiling
Cable Tray Works / Installation of Gantry SupportInstallation of Lighting Pole / Installation of Fencing Gate
September 02, 2012 - Transformer A Test Preparation / Installation of Sunshields for GIS / Earthing Lightning Works -Container B
Backfilling for Earthing_GIS_NE area